What to Know
- MARA Holdings priced $185 million in new debt at an 8.75% interest rate to help finance its roughly $1.5 billion acquisition of Long Ridge Energy & Power.
- The transaction is expected to close Nov. 27 and includes existing debt tied to Long Ridge.
- The deal includes a 485-megawatt natural-gas power plant in Hannibal, Ohio, and more than 1,600 acres of land.
- MARA plans to develop the site into a computing campus serving artificial intelligence customers.
- The new borrowing follows MARA’s sale of $1.1 billion in bitcoin after September.
- MARA sold 13,597 BTC at an average price of about $81,039 and used $750 million of proceeds to repay loans secured by its bitcoin reserves.
- Long Ridge generated $178.5 million in revenue during the first nine months of 2026 and recorded a $3.5 million net loss.
- MARA shares rose about 4.7% to $6.72 in early Wednesday premarket trading after falling 3.3% to $6.42 on Tuesday.
- The stock remains down roughly 12.5% since Nov. 10 as weaker bitcoin prices and the AI infrastructure shift shape investor sentiment.
MARA Adds Debt as It Repositions Beyond Bitcoin Mining
MARA Holdings is adding another layer of financing to its business as the bitcoin miner pushes deeper into power ownership and artificial intelligence infrastructure. The company has priced $185 million in new debt at an 8.75% interest rate through a subsidiary connected to Long Ridge Energy & Power, the Ohio power business MARA is moving to acquire.
The financing is designed to help support MARA’s roughly $1.5 billion acquisition of Long Ridge Energy & Power, a transaction that includes existing debt and is expected to close Nov. 27. The deal gives MARA control of a 485-megawatt natural-gas power plant in Hannibal, Ohio, along with more than 1,600 acres that the company intends to develop into a large computing campus for artificial intelligence customers.
The move highlights a broader strategic shift among major bitcoin miners. With mining economics still closely tied to bitcoin prices, network competition, energy access and capital costs, some operators are seeking to convert power assets and data-center experience into services for high-performance computing and AI workloads. MARA’s transaction fits squarely within that theme, though it also raises questions about leverage, execution risk and the timing of expansion while bitcoin-linked equities remain under pressure.
New Bonds Follow a Major Bitcoin Sale
The latest borrowing comes shortly after MARA sold $1.1 billion in bitcoin. The company sold 13,597 BTC at an average price of about $81,039 after September, using $750 million of the proceeds to repay cryptocurrency-backed loans that had helped finance the Long Ridge acquisition.
That sequence is important because it shows a change in the way MARA is funding the deal. The earlier loans were secured against the company’s bitcoin reserves, exposing the balance sheet to the risks that can emerge when crypto prices fall and collateral values decline. By repaying those cryptocurrency-backed loans and replacing part of the financing with borrowing tied to the acquired power business, MARA is shifting the structure of its obligations away from direct bitcoin-collateralized debt.
For bitcoin miners, treasury management has become a central part of the business model. Companies that hold large BTC reserves can benefit when prices rise, but those reserves can also become a source of liquidity when cash is needed for debt repayment, acquisitions or infrastructure expansion. MARA’s sale of bitcoin therefore represents both a funding decision and a signal that the company is willing to use its crypto holdings to support a broader infrastructure strategy.
Long Ridge Debt Load and Interest Costs Come Into Focus
The new bonds will be issued by Long Ridge, which already has $600 million in notes carrying a similar 8.75% interest rate. Once the additional borrowing is completed, annual interest payments on the combined $785 million would reach approximately $68.7 million. The new borrowing alone would add about $16.2 million in annual interest.
Those interest costs will be closely watched by investors because the acquisition brings both infrastructure assets and financial obligations. Long Ridge is not simply a speculative development project; it already operates a power business that generated $178.5 million in revenue during the first nine months of 2026. However, financial statements filed Monday showed the business recorded a $3.5 million net loss over that period.
MARA has previously estimated Long Ridge’s annualized adjusted earnings at $144 million, based on the second half of 2025. Market participants are likely to focus on whether the acquired business can support its debt costs while also funding the buildout of AI-focused computing capacity. The difference between revenue, net income and adjusted earnings will remain important as investors assess how much cash the power business can produce after operating costs, financing costs and development spending.
Ohio Power Plant Becomes the Center of the AI Push
The Long Ridge asset centers on a 485-megawatt natural-gas power plant in Hannibal, Ohio. For a bitcoin miner, direct access to significant power capacity can be strategically valuable because electricity is one of the largest operating inputs in mining. For an AI infrastructure platform, power availability is also critical, as large-scale computing campuses require stable and substantial energy supply.
The more than 1,600 acres included in the transaction give MARA physical room to pursue a broader data-center development plan. The company wants to turn the site into a computing campus for artificial intelligence customers, a market that has attracted substantial interest from infrastructure providers because AI workloads require specialized equipment, dense power delivery and reliable cooling and connectivity.
MARA has reported interest from prospective large-scale customers and is targeting two data-center leases before year-end. At the same time, the company has warned that negotiations could extend into 2027. That caveat matters because signing leases is a key step in converting an infrastructure vision into contracted revenue. Until agreements are finalized, the timing and scale of the AI opportunity remain uncertain.
Shares Rebound in Premarket but Remain Under Pressure
MARA shares rose about 4.7% to $6.72 in early Wednesday premarket trading, recovering part of Tuesday’s 3.3% decline to $6.42. Despite that rebound, the stock remains down roughly 12.5% since Nov. 10.
The share-price reaction reflects a mixed backdrop. On one hand, investors may view the debt pricing and acquisition financing as evidence that MARA is advancing a plan to diversify beyond traditional bitcoin mining. On the other hand, the added debt, the sale of a large amount of bitcoin and the uncertainty around AI lease timing may keep pressure on the stock.
Falling bitcoin prices are also weighing on the outlook. Bitcoin miners often trade as high-beta proxies for BTC because their revenue, balance sheets and investor narratives are connected to the cryptocurrency’s price. When bitcoin weakens, mining stocks can face amplified pressure, particularly if companies are also making large capital commitments or changing their business mix.
Why the Deal Matters for Bitcoin Miners
MARA’s Long Ridge financing illustrates how the bitcoin mining sector is evolving. The original mining model centered on acquiring machines, securing low-cost power and producing BTC. That model still matters, but the growing demand for AI computing has created a parallel opportunity for miners with energy assets, land, electrical infrastructure and data-center operational experience.
Some chart watchers and equity market participants see this transition as potentially supportive over the long run because AI customers may provide more predictable contracted revenue than bitcoin mining alone. However, the transition is not automatic. Data-center customers often require rigorous performance standards, significant capital investment and long negotiation timelines. A power plant and land package can create a foundation, but commercial success depends on execution.
For MARA, the Long Ridge acquisition is therefore more than a power deal. It is a test of whether a large bitcoin miner can turn energy infrastructure into a platform for AI computing while managing debt and retaining enough exposure to bitcoin to satisfy investors who originally bought the stock for crypto-linked upside.
Balance Sheet Strategy Takes Center Stage
The company’s decision to sell 13,597 BTC and repay $750 million in crypto-backed loans shows a more active balance sheet approach. Crypto-backed loans can provide liquidity without immediately selling bitcoin, but they can also create risk when market prices move sharply. By reducing that exposure, MARA has changed the risk profile of the acquisition financing.
At the same time, new debt at an 8.75% interest rate is not inexpensive. The combined Long Ridge notes would carry significant annual interest payments, and investors will want to see whether operating cash flow and future data-center leases can justify the capital structure. If AI-related demand converts into signed agreements, the acquisition could broaden MARA’s revenue base. If negotiations stretch further into 2027 without firm commitments, market scrutiny could increase.
The next major milestones are the expected close of the transaction on Nov. 27 and any updates on potential data-center leases before year-end. Until then, MARA’s stock is likely to remain sensitive to both bitcoin price action and investor confidence in the company’s AI infrastructure pivot.
Frequently Asked Questions (FAQs)
What did MARA announce?
MARA Holdings priced $185 million in new debt at an 8.75% interest rate to help finance its roughly $1.5 billion acquisition of Long Ridge Energy & Power.
When is the Long Ridge transaction expected to close?
The acquisition is expected to close Nov. 27, and the transaction includes existing debt tied to Long Ridge Energy & Power.
What assets are included in the Long Ridge deal?
The deal includes a 485-megawatt natural-gas power plant in Hannibal, Ohio, and more than 1,600 acres that MARA plans to develop into an AI computing campus.
How much bitcoin did MARA sell?
MARA sold 13,597 BTC after September at an average price of about $81,039, generating $1.1 billion in proceeds.
Why did MARA sell bitcoin?
MARA used $750 million of the bitcoin sale proceeds to repay loans secured against its bitcoin reserves, loans that had helped finance the Long Ridge acquisition.
What are the expected interest costs tied to the Long Ridge notes?
Long Ridge already has $600 million in notes at a similar 8.75% interest rate, and after the new borrowing, annual interest payments on the combined $785 million would reach approximately $68.7 million.
How is Long Ridge performing financially?
Long Ridge generated $178.5 million in revenue during the first nine months of 2026 and recorded a $3.5 million net loss during that period.
How did MARA shares react?
MARA shares rose about 4.7% to $6.72 in early Wednesday premarket trading after falling 3.3% to $6.42 on Tuesday, though the stock remains down roughly 12.5% since Nov. 10.
Why is MARA moving into AI infrastructure?
MARA is seeking to use power assets, land and computing infrastructure to serve artificial intelligence customers, potentially diversifying beyond bitcoin mining, though lease negotiations could extend into 2027.